2009 – BWW HILITES – DECEMBER 2009
FINANCIALS:
A       -FY 2009 BUDGET $3.15 MM, OPERATING $1.6MM, DEBT (BONDS & LOANS) PAYMENT $1.44MM – PER YR
B       -FY 2010 BUDGET $3.10 MM, OPERATING $1.6MM, DEBT (BONDS & LOANS) PAYMENT $1.39MM - PER YR
C       -FY 2010 TOTAL OUTSTANDING DEBT = $9.8MM – (PRINCIPLE & INTEREST) DEBT PAYMENT DECREASE FY – 2010 = 47K
D       -FY 2011 FORECAST – TOTAL OUTSTANDING DEBT (OLD) = $8.4MM – DEBT PAYMENT DECREASE -2011 = $48K
E       -NEW DEBT WILL RESULT FROM THE NHSRL FY 2009 – ($3,000,000 @ 50% FORGIVENESS)
F       -NEW DEBT WILL RESULT FROM THE USDA RUD LOANS & GRANTS FY 2009 (2) – ($4,900,000 @ 25% LOANS)
G       -FY 2011 OUTSTANDING EQUIPMENT DEBT (PRINCIPLE & INTEREST) = $156,776-CAT BACK-HOE, KOMAT’SU LOADER & EXCAVATOR/HAMMER, & M&M GARAGE (+$12,250 BALANCE DUE IN MAY 2010)

CONTINUED HIGH LEVEL OF “FORCE ACCOUNT” ACTIVITY
1       -THE BALANCE OF GRANT FUNDING FOR JAN 2009 WAS LESS THAN $1,500,000–SPENT $900,000(OLD $)–JAN 2009-THRU-DEC 2009=$600,000
2       -BALANCE OF (OLD$) JANUARY 2010 = $600,000.
3       -MAINTAINED TWO (2) MAIN LINE CREWS AND A SERVICE LINE/MAINT. CREW
4       -HIRED A 7TH FULL TIME HOURLY EMPLOYEE – (JG)
5       -HIRED 5 EXPERIENCED TEMPORARY EMPLOYEES – APRIL THRU NOVEMBER
6       -PURCHASED USED 21 TON TRAILER FOR CAT 315 EXCAVATOR (2ND)
7       -PURCHASED TWO (2) COMPACTORS – LAJOIE & AUCTION
8       -PURCHASED TWO (2) TRENCH BOXES @ AUCTION
9       -PURCHASED USED CAT 322BL EXCAVATOR @ AUCTION
10      -PURCHASED NEW PAVEMENT CUTTING MACHINE
11      -MANAGING $9MM – ENGINEERING AND CONSTRUCTION OF BWW IMPROVEMENT PROJECTS

“FORCE ACCOUNT PROJECTS” – INSTALLED 4613 LIN FT OF WATER MAIN W/BWW CREWS & EQUIPMENT           #OF FT  INSTALLED
a       WESTCOTT STREET – 2-INCH – DEAD END –EPA                                                                                188
b       MAIN STREET – HIGH TO RR – 2-INCH –DEAD END -EPA                                                                         NR
c       12TH STREET- ALPINE ST TO DEAD END-EPA                                                                                  NA
d       SCHOOL ST – SUCCESS TO CAMBRIDGE-EPA                                                                                    307
e       FIRST (ABENAKI LN) & MAIN ST INTERSECTION-EPA                                                                           332
f       RESCOPED – RUD- FORBUSH TIDE-FLEX HEADERS                                                                               96
g       RESCOPED – RUD- LOWER RIVER ST TO ROCKY LANE (DEAD RIVER CROSSINGS – TWO)                                       1482
h       RESCOPED – RUD- RR CROSSING – ROCKY LANE – RIVER ST                                                                     204.5
i       RESCOPED – RUD – RR CROSSING – RIVER ST – MADISON AVE TIE-IN                                                            34
j       RESCOPED – RUD – RR CROSSING – NIBROC – WESTERN AVE                                                                     96
k       RESCOPED – RUD – RR CROSSING – GLEN AVE – WESTERN AVE                                                           164
l       RESCOPED – RUD – LANCASTER TANK MIXING – PAX SYSTEM W/TEMPERATURE MONITORING                            -
m       GOEBEL STREET – MASON ST TO DEVENS ST – NHSRL #7                                                                        1147
n       MERRIMACK STREET – GOEBEL STREET – TO DEAD END – 2-INCH –NHSRL #7                                               150
o       BURGESS STREET – MASON ST TO GRAFTON ST- NHSRL #7                                                                       412.5
                                                                                                                                        
OTHER IMPROVEMENTS:
1       APPLIED FOR STIMULUS FUNDING (4 APPLICATIONS) & REQUESTED STAG GRANTS (2)
2       RECEIVED NHSRL PACKAGE, ONE STAG GRANT(PENDING), AND TWO RUD PACKAGES PENDING
3       DUE TO NEW FUNDING, IDENTIFIED NEED TO SCALE UP “FORCE ACCOUNT” – MAY HAVE TO ADJUST FY 2010 BUDGET BY AS MUCH AS $250,000
4       SCALE UP “FORCE ACCOUNT” – PURCHASED 3RD EXCAVATOR(USED CAT 322BL), ONE DUMP TRUCK (USED), TWO VIB COMPACTORS(USED), TWO TRENCH BOXES (USED), PAVEMENT CUTTER(NEW), - LOOKING FOR LOADER, SKID STEER, THUMB, & DUMP TRUCKS
5       CONTINUED TO OPERATE WITH – DOWNSIZED –STAFFING – ADDED ONE IN 2009 = 14 FULL TIME EMPLOYEES ( FROM 19 IN 2000)
6       ORDERED TWO (2) NEW FORD PICK-UP TRUCK – FOR MARCH 2010 DELIVERY – ($18,000/EA)
7       COMPLETED – STAGE 2 DISINFECTION BYPRODUCT & LT 2 RULE TESTING – COMPLIANCE REQUIREMENT
8       RUNNING WATER PROGRAM – EARLY RUNNING WATER DOWN TO 109 CUSTOMERS REMAINING. (REMOVED 13 FROM LIST IN 2009)(OVER 1000 IN 2000)
9       GODFREY DAM PROJECT – PHASE II – ENG CONTRACT SIGNED - FUNDING REQUEST USDA RD-CONSTRUCTION PLAN 2010- REQ’D TO MEET NHDES DAM BUREAU MANDATE
10      SEPT 2009 – PASSED LEAD & COPPER COMPLIANCE TEST (6TH CONSECUTIVE)-CONTINUED IMPROVING RESULTS IN REDUCED TESTING (30 SAMPLES)/EVERY 3 YEARS
11      CONTINUED TO REDUCE UNPLANNED WORK LEVELS WITH SYSTEM IMPROVEMENT PROJECTS.
12      JOHN ARSENAULT – TESTING BACK-FLOW PREVENTORS, INSTALLED CHLORINE ANALYSERS AT PRV AND TANKS, TEMPS IN LANCASTER, OTHER PROCESS IMPROVEMENTS – INSTALLED ACCESS PALTFORMS TO STORAGE TANKS.
13      UPGRADED 163 WATER METERS & INSTALLED 205 BACKFLOW PREVENTORS & ALL CUSTOMERS ARE METERED. 23 ACTIVE/32 INACTIVE METERS REMAINING TO UPGRADE.
14      OFFICE STAFF – NDS SYSTEM – AUTO BACK-UP PROGRAM ESTABLISHED – NEW ASSESSMENT RATE SYSTEM (STARTED MAY 2009).
15      IMPROVED APPEARANCE – CLEANED UP REMOVED FENCE, PAINTED M & M GARAGE @ 55 WILLOW STREET – READY TO INSTALL NEW BWW SIGNS.
16      DEFERRED FOLLOW-UP WORK ON MAJOR MAIN LINE LEAK IN 16-INCH MAIN IN RIVER @ MASON STREET – CORROSION ISSUE
17      SCADA SYSTEM IMPROVEMENTS – PURCHASED SOFTWARE TO TROUBLESHOOT & REBOOT SYSTEM W/BWW STAFF
18      SAFETY- INSPECTIONS BY NH DEPARTMENT OF LABOR.TRENCH/EXCAVATION VIOLATION – PAID FINE.
19      SAFETY IMPROVEMENTS – INSTALLED ROOF OVER AMMO EXIT W/CONEX AND INSTALLED ROOF OVER LEAKAGE AREA
20      IN YEAR 4 OF 5 YEAR NEGOTIATED UNION LABOR CONTRACT
21      UTILIZING BENEFITS FROM HOURLY PARTICIPATION IN REVISED COVERAGE PROCESS ( TREATMENT & DRISTRIBUTION ).
22      2009- 4 MAIN LINE BREAKS AND 3 SERVICE LINE BREAKS
23      CONTINUE TO REVISE ALL BWW DISTRIBUTION SYSTEM DRAWINGS IN AUTOCAD
24      BROWN FARM WELL – WELLHEAD PROTECTION STUDY ON-GOING & REPLACED WELL PUMP MOTOR (MOTOR FAILED)
25      DEWATERED & CLEANED LANCASTER & AMMO STORAGE TANKS & AMMO SLUDGE BASINS (2) W/BWW STAFF.
26      ESTABLISHED REQUIRED “ RED FLAG POLICY”



 